We have started preparing the PowerPoint for the presentation. Sarah and Stuart are working on the main graphics. Everyone else has to make their own slides using those backgrounds.
Aaron 1 has nearly finished the coding for the website.
Jay and Igor are finalising the in game videos.
Aaron 3 is working on the Game Lore/How to play text.
We have also just had a progress meeting with Phil and Travis. We went though the assessment sheet and checked our progress.
We are about a week behind.
Everyone has to work out what they are going to talk about in the presentation and start working on their PowerPoint slides.
We also have to divvi up the group documents, time line etc, to whoever is going to talk about them.
Project Brief - Aaron has already typed it up
Project and Actual Time lines - Aaron typed up the projected. Sarah is laying out the actual
Product Backlog - which is the list of requirements.
Task List - the info is on the blog
Product Standards and Established Systems - team roles and responsibilities, documentation standards, file naming conventions
Minutes of Meetings - on blog
Project Retrospective Report - what went well and what could have been better.